What this topic covers

Public works for the Law and Business Examination: what counts as a public work, contractor registration, prevailing wages, certified payroll records, apprentices, hours, workers' compensation certification, payment bonds and retention. These are original practice notes, not materials of the CSLB or PSI, based on California texts in force on January 1, 2027, as read in November 2026. Dollar thresholds and percentages are those of that text and can change.

Public works and registration

Prevailing wage

Certified payroll records

Apprentices, hours and insurance

Bonds, retention and debarment

Common traps

Take the free test · full question bank and mock exams with a subscription

Sample questions (5)

1. Under Labor Code section 1720, which BEST describes “public works”?

  1. Any work performed on land owned by a public agency, no matter who pays for it or hires the crew
  2. Construction work that a public agency performs using its own employees, equipment, and funds
  3. Any private project that a public agency inspects, regulates, and issues building permits for
  4. Construction or repair work done under contract and paid for at least partly with public funds

Labor Code section 1720(a)(1) defines public works as “Construction, alteration, demolition, installation, or repair work done under contract and paid for in whole or in part out of public funds”. Land ownership alone does not make work a public work. Work a public agency performs with its own employees is not done under contract, and section 1771 makes the prevailing wage requirement inapplicable to work carried out by a public agency with its own forces. A permit or inspection by a public agency does not involve public funds.

2. What is the MAXIMUM public works project amount that is exempt from the prevailing wage requirement under Labor Code section 1771?

  1. $1,000
  2. $15,000
  3. $25,000
  4. $100,000

Labor Code section 1771 requires prevailing wages “Except for public works projects of one thousand dollars ($1,000) or less”. The $15,000 and $25,000 figures are the registration exemption amounts in section 1725.5(f), not the exemption in section 1771, and $100,000 appears in neither section. Amount from the Labor Code text read on 11/13/2026.

3. Under Labor Code section 1725.5, by what date each year must a contractor pay the renewal fee for its DIR public works registration?

  1. On or before January 1
  2. On or before March 1
  3. On or before July 1
  4. On or before October 1

Labor Code section 1725.5(a)(1) requires an annual renewal fee “on or before July 1 of each year thereafter”, and under subdivision (c) a contractor that misses it may not bid on or perform public work until it is registered again. March 1 and January 1 appear in section 1725.5(e) only as the 2015 and 2018 starting dates of the registration requirements, not as renewal dates, and October 1 is not a date in section 1725.5.

4. A city hires Bayview Builders, Inc., a licensed contractor, under a $20,000 contract to build a new storage shed at a city park. Bayview is not registered with the DIR. Under Labor Code section 1725.5, is registration required?

  1. Yes, because construction projects over $15,000 require registration
  2. No, because construction projects of $25,000 or less are exempt
  3. Yes, because any public works project over $1,000 requires registration
  4. No, because the city may waive registration for a licensed contractor

Labor Code section 1725.5(f) says the section does not apply to work on a public works project of “twenty-five thousand dollars ($25,000) or less when the project is for construction, alteration, demolition, installation, or repair work”, so the $20,000 shed contract does not require registration. The $15,000 limit in subdivision (f) applies to maintenance work, not to construction. The $1,000 figure is the prevailing wage exemption in section 1771, not a registration threshold, so prevailing wages are still owed on this project. Nothing in section 1725.5 lets an awarding body waive registration. Amounts from the Labor Code text read on 11/13/2026.

5. Who determines the general prevailing rate of per diem wages for each craft in a locality for public works contracts?

  1. The public body awarding the contract
  2. The office of the Labor Commissioner
  3. The Registrar of Contractors' office
  4. The Director of Industrial Relations

Labor Code section 1773 requires the body awarding a contract to obtain the general prevailing rate of per diem wages “from the Director of Industrial Relations”. The awarding body obtains and specifies the rates rather than setting them. Neither the Labor Commissioner's office nor the Registrar of Contractors determines the rates.