What this topic covers
Framing and structural components for the General Building (B) Examination: floor and wall framing, roof framing and trusses, seismic hardware, and exterior work (stucco, decks, stairs). These are original practice notes, not materials of the CSLB or PSI. Code sections refer to the 2025 California Building Standards Code (Title 24), to be checked in the edition in force; site knowledge follows standard methods of the trade.
Floor framing
- Sill plate (mudsill): lowest wood member; it rests on and is anchored to the foundation. The rim (band) joist sits on it and closes the joist ends.
- Joist ends: a minimum bearing length, or an approved joist hanger rated for the joist (California Residential Code Section R502.6 (check the current code)). Toenails or adhesive are not a structural end connection.
- Bored holes: size limited by joist depth and kept away from edges and other holes or notches (California Residential Code Section R502.8 (check the current code)). Mid-depth carries the least bending stress.
- Subfloor: long dimension perpendicular to the joists (California Residential Code Section R503.2 (check the current code)), staggered end joints for a continuous diaphragm, and a gap because panels swell with moisture.
Wall framing
- King, jack and cripple studs: king = full height beside an opening; jack = carries the header end; cripple = any stud shorter than full height.
- Missing jacks: side nails then carry the header load in shear, and the header can slip and sag.
- 16-inch spacing: divides evenly into 48 inches, so 4-foot panel edges land on studs.
- Fireblocking: stops flame through concealed spaces, including at floor and ceiling levels (California Residential Code Section R602.8 (check the current code)). Racking resistance comes from bracing and sheathing.
- Green lumber: shrinks and twists as it dries, causing nail pops.
Roof framing and trusses
- Pitch: inches of rise per 12 inches of run. Rise 5 feet over run 15 feet: 5 / 15 x 12 = 4:12.
- Rafter length: square root of (run squared + rise squared). A 12-foot run at 6:12 gives the square root of 180 = 13.4 feet.
- Roof surface: plan area with overhangs x slope factor: (44 + 4) x (30 + 4) = 1,632 square feet x 13/12 = 1,768 square feet.
- Trusses: lift at pick points, brace each as it is set, store flat on level blocking; no cut or notch without a registered design professional (California Residential Code Section R802 (check the current code)).
- Attic ventilation: sized by net free ventilating area (California Residential Code Section R806 (check the current code)), low intake at the soffit, high exhaust at the ridge.
Seismic hardware and load path
- Anchor bolts: keep walls from sliding or lifting off the foundation; one near each end of every plate section (California Residential Code Section R403.1.6 (check the current code)).
- Plate washers: in Seismic Design Categories D0, D1 and D2 unless approved anchor straps are used (California Residential Code Section R602.11.1 (check the current code)).
- Continuous load path: roof-to-wall ties (hurricane ties against uplift), hold-downs and anchor bolts joined by the framing.
- Shear walls: overdriven nails crush the panel; blocked edges let shear pass between panels.
- Misplaced hold-down anchor: the designer approves the repair; never bend, relocate or cut it.
Exterior, decks and stairs
- Stucco: keep the scratch coat damp; control joints steer cracking; the weep screed drains the base.
- Guard height: measured vertically from the walking surface or tread nosings (California Residential Code Section R312 (check the current code)).
- Unit rise: total rise / number of risers: 105 / 14 = 7.50 inches (not the number of treads).
- Wildfire areas: vents must resist flames and embers (California Residential Code Section R337 (check the current code)).
Sample questions (5)
1. Which framing member is bolted directly to the top of a concrete foundation stem wall and supports the floor system?
- Sill plate on the foundation
- Rim joist on top of the sill plate
- Double top plate at the wall head
- Ledger board on the face of a beam
The sill plate (mudsill) is the lowest wood member of the structure; it rests on the foundation, is anchored to it, and receives the floor framing. The rim joist sits on top of the sill plate and closes the ends of the joists. The top plate caps a stud wall at the ceiling level. A ledger board is fastened to the face of a wall or beam to carry joist ends.
2. In a framed door opening, which stud carries the end of the header directly from below?
- King stud beside the opening frame
- Jack stud under the header end
- Cripple stud over the header span
- Common stud in the open wall field
The jack stud (trimmer) is cut to the height of the opening and supports the end of the header. The king stud runs full height beside the jack stud and braces it. A cripple stud is a short stud above the header or below a window sill. A common stud is an ordinary full-height wall stud away from the opening.
3. Which description fits a cripple stud?
- A full-height stud placed right beside an opening
- A stud cut to carry the end of a header
- A short stud above a header or below a sill
- A stud that forms the corner of two walls
A cripple stud is any stud that does not run the full height from the bottom plate to the top plate; examples are the short studs above a header or below a window sill. A full-height stud beside an opening is a king stud. A stud cut to carry the end of a header is a jack stud. A stud that forms the corner of two walls is a corner stud, which is full height.
4. Which framing method uses studs that run in one piece from the sill to the top plate, with the upper floor joists resting on a ribbon let into the studs?
- Platform framing method
- Timber framing method
- Modular framing method
- Balloon framing method
In balloon framing the wall studs are continuous past the floor levels and the upper floor joists rest on a ribbon let into the studs, so fireblocking is needed at each floor. In platform framing each story is built on the deck of the story below and the studs are one story tall. Timber framing relies on widely spaced posts and beams rather than closely spaced studs. Modular framing refers to factory-built units set on the foundation, not to the way studs run.
5. What is the member called that runs around the perimeter and closes the ends of the floor joists in a platform-framed floor?
- Rim joist on the sill
- Girder beam under the floor
- Bridging between joists
- Header over a wall opening
The rim joist (also called a band joist) sits on the sill plate, closes the ends of the floor joists, and supports the wall above. A girder is a main beam that carries the ends of joists inside the building. Bridging is placed between joists to stiffen the floor. A header spans a wall opening and has nothing to do with the floor perimeter.