Section 3 of the General Building (B) Examination: the core trades a B contractor coordinates and inspects. These are original practice notes, not materials of the CSLB or PSI. Trade knowledge uses standard trade methods; code values come from the 2025 California Building Standards Code (Title 24), to be checked in the edition in force; excavation and jobsite rules follow California texts in force on January 1, 2027.
1. A continuous footing is 2 feet wide, 1 foot deep and 60 feet long. How many cubic yards of concrete are needed, with no waste allowance?
Volume is 2 x 1 x 60 = 120 cubic feet, and 120 / 27 = 4.44 cubic yards. Dividing by 9 uses the square-yard factor, dividing by 3 uses the linear-yard factor, and leaving 120 forgets to convert cubic feet to cubic yards.
2. A slab is 24 feet by 30 feet and 4 inches thick. If 10 percent of the net volume is added for waste, how many cubic yards should be ordered?
The net volume is 24 x 30 x (4 / 12) = 240 cubic feet, or 8.89 cubic yards, and adding 10 percent gives 240 x 1.10 / 27 = 9.78 cubic yards. A figure of 8.89 leaves out the waste, 9.88 divides by 0.90 as if the waste were a share of the ordered amount, and 117.33 treats the 4 inches as 4 feet.
3. Four round concrete piers are each 18 inches in diameter and 6 feet deep. Using pi = 3.14, how many cubic yards of concrete are needed for all four?
The radius is 0.75 foot, so each pier holds 3.14 x 0.75 x 0.75 x 6 = 10.60 cubic feet; four piers hold 42.39 cubic feet, or 1.57 cubic yards. A figure of 0.39 counts one pier only, 0.50 leaves out pi, and 6.28 uses the diameter as the radius.
4. Each bag of dry mix yields 0.45 cubic foot of concrete. How many bags are needed to fill a form that holds 9 cubic feet?
The number of bags is 9 / 0.45 = 20. Multiplying 9 by 0.45 instead of dividing gives about 4 bags, 200 comes from misplacing the decimal point in the yield (0.045 cubic foot), and 540 multiplies by 27 as if the form held 9 cubic yards instead of 9 cubic feet.
5. A 20-foot by 30-foot slab uses No. 4 bars at 12 inches on center in both directions, with a bar at each edge. Ignoring laps and cover, how many feet of bar are needed?
Bars running 30 feet: 20 / 1 + 1 = 21 bars, or 630 feet. Bars running 20 feet: 30 / 1 + 1 = 31 bars, or 620 feet. The total is 1,250 feet. A total of 630 counts one direction only, 1,200 forgets the extra bar at the last edge, and 2,450 uses 6-inch spacing.