What this topic covers
Contract Requirements and Execution on the Law and Business Examination: public bidding, cost and schedule control, home improvement contracts, payments and retention, claims and limitation periods. These are original practice notes, not materials of the CSLB or PSI, based on California law in force on January 1, 2027. Dollar amounts and caps were read in 2026 and change.
Public bidding
- License classification: stated in the notice inviting bids and held at the time of award (Public Contract Code section 3300).
- Subcontractor listing: only one subcontractor for each portion (section 4104); substitution needs consent on grounds such as insolvency, no license, or failure or refusal to perform, never a lower price (section 4107); 10 percent penalty for listing violations (section 4110).
- Bid shopping: using one subcontractor's price to push others lower. Bid peddling is a sub undercutting after bids; bid rigging is collusion.
- Bid mistakes: no relief for carelessness in inspecting the site or reading the plans (section 5103); the bidder may not bid again on that project (section 5105).
- Additive items: with no specification, the lowest base bid wins (section 20103.8).
Cost and schedule control
- Change order: priced, signed and approved before extra work starts. An RFI clarifies the plans; a submittal approves products.
- Bid price: cost + overhead, then profit on that total: $210,000 x 1.10 = $231,000.
- Critical path: the longest chain of activities. The right to damages for unreasonable delay caused by the agency is kept (Public Contract Code section 7102).
Home improvement contracts
- Home improvement: repairing, remodeling or altering residential property, including fences, landscaping and garages (Business and Professions Code section 7151).
- Salesperson: a corporate officer of record listed as personnel is exempt (section 7152); a security interest is unenforceable if an unregistered salesperson sold the contract (section 7153).
- Downpayment: $1,000 or 10 percent of the contract amount, whichever is less (section 7159.5).
- Type: printed text at least 10-point; the downpayment statement in 12-point boldface (section 7159).
- Right to cancel: three business days, five for a senior citizen aged 65 or older (Civil Code section 1689.5), seven for repairs after a declared disaster; it starts when the buyer receives the signed copy (Civil Code section 1689.6).
- Change order: scope, amount added or subtracted, effect on payments or completion date (section 7159.6).
- Service and repair contract: $750 or less, among other conditions (section 7159.10).
- Indemnity: provisions covered by Civil Code section 2782 are void and unenforceable, for injury, death or property loss; initialing them does not help.
Payments and retention
- Owner progress payment: within 30 days after notice demanding payment (Civil Code section 8800).
- Retention: private owner, 45 days after completion (section 8812); a 10-day retention period under section 8814; public entity, 60 days (Public Contract Code section 7107).
- Prompt payment: subs paid within 7 days after receipt of each progress payment unless otherwise agreed in writing; up to 150 percent of a disputed amount may be withheld; 2 percent per month penalty and attorney's fees (Business and Professions Code section 7108.5).
Claims and time limits
- Public claims: written, documented, filed on or before final payment (Public Contract Code section 20104.2).
- Written contract: four years (Code of Civil Procedure section 337); latent deficiencies, 10 years (section 337.15).
- Builder: a general contractor acting only as such is not the builder (Civil Code section 911).
Sample questions (5)
1. Under Public Contract Code section 3300, what must a public entity specify in the notice inviting bids for a public project?
- The minimum years of licensed experience
- The license classification needed at award
- The maximum dollar value per subcontract
- The surety company the bidder must use
Public Contract Code section 3300 requires the public entity to specify the classification of the contractor license that a contractor must possess “at the time a contract is awarded”, and to include it in the notice inviting bids. The section says nothing about years of experience, a cap on subcontract amounts, or a required surety company.
2. A prime contractor inadvertently lists a wrong license number for a listed subcontractor, but the name and location are correct. To keep the bid responsive, when must the corrected number be submitted?
- Within 24 hours after bid opening
- Within 48 hours after bid opening
- Within 72 hours after bid opening
- Within 5 days after bid opening
Public Contract Code section 4104 provides that the error is not grounds for a bid protest or for finding the bid nonresponsive if the corrected number is submitted “within 24 hours after the bid opening” and matches the listed name and location. The 48-hour, 72-hour and 5-day periods are not the period in section 4104.
3. When a prime contractor lists subcontractors in a public works bid under section 4104, how many may be listed for each portion of the work?
- Two, with one named as the alternate
- Three, ranked in order of price
- Any number the prime contractor names
- Only one subcontractor for each portion
Public Contract Code section 4104 states that the prime contractor shall “list only one subcontractor for each portion” of the work, as the prime contractor defines the portion in the bid. Naming an alternate, ranking several firms by price, or listing any number of firms is not permitted by the section.
4. The awarding authority notifies a listed subcontractor of a request to substitute it. Within how many working days must written objections be filed?
- Three working days
- Five working days
- Seven working days
- Ten working days
Under Public Contract Code section 4107 the listed subcontractor has “five working days within which to submit written objections” to the substitution, and failing to object counts as consent. Three, seven and ten working days are not the period in section 4107.
5. A bidder on a public project claims a mistake in its bid. Under Public Contract Code section 5105, what is the result for that bidder?
- It must pay a 10 percent penalty to the agency
- It is suspended from public bidding for a year
- It may not bid again on that same project
- It must surrender its contractor license for review
Public Contract Code section 5105 says a bidder who claims a mistake is “prohibited from participating in further bidding on the project” on which the mistake was claimed. The 10 percent penalty belongs to section 4110 (subcontractor listing violations), and section 5105 sets no statewide suspension or license surrender.