CAContractorLicenseExam

✍️ Contract Requirements and Execution

What this topic covers

Contract Requirements and Execution on the Law and Business Examination: public bidding, cost and schedule control, home improvement contracts, payments and retention, claims and limitation periods. These are original practice notes, not materials of the CSLB or PSI, based on California law in force on January 1, 2027. Dollar amounts and caps were read in 2026 and change.

Public bidding

Cost and schedule control

Home improvement contracts

Payments and retention

Claims and time limits

Take the free test · full question bank and mock exams with a subscription

Sample questions (5)

1. Under Public Contract Code section 3300, what must a public entity specify in the notice inviting bids for a public project?

  1. The minimum years of licensed experience
  2. The license classification needed at award
  3. The maximum dollar value per subcontract
  4. The surety company the bidder must use

Public Contract Code section 3300 requires the public entity to specify the classification of the contractor license that a contractor must possess “at the time a contract is awarded”, and to include it in the notice inviting bids. The section says nothing about years of experience, a cap on subcontract amounts, or a required surety company.

2. A prime contractor inadvertently lists a wrong license number for a listed subcontractor, but the name and location are correct. To keep the bid responsive, when must the corrected number be submitted?

  1. Within 24 hours after bid opening
  2. Within 48 hours after bid opening
  3. Within 72 hours after bid opening
  4. Within 5 days after bid opening

Public Contract Code section 4104 provides that the error is not grounds for a bid protest or for finding the bid nonresponsive if the corrected number is submitted “within 24 hours after the bid opening” and matches the listed name and location. The 48-hour, 72-hour and 5-day periods are not the period in section 4104.

3. When a prime contractor lists subcontractors in a public works bid under section 4104, how many may be listed for each portion of the work?

  1. Two, with one named as the alternate
  2. Three, ranked in order of price
  3. Any number the prime contractor names
  4. Only one subcontractor for each portion

Public Contract Code section 4104 states that the prime contractor shall “list only one subcontractor for each portion” of the work, as the prime contractor defines the portion in the bid. Naming an alternate, ranking several firms by price, or listing any number of firms is not permitted by the section.

4. The awarding authority notifies a listed subcontractor of a request to substitute it. Within how many working days must written objections be filed?

  1. Three working days
  2. Five working days
  3. Seven working days
  4. Ten working days

Under Public Contract Code section 4107 the listed subcontractor has “five working days within which to submit written objections” to the substitution, and failing to object counts as consent. Three, seven and ten working days are not the period in section 4107.

5. A bidder on a public project claims a mistake in its bid. Under Public Contract Code section 5105, what is the result for that bidder?

  1. It must pay a 10 percent penalty to the agency
  2. It is suspended from public bidding for a year
  3. It may not bid again on that same project
  4. It must surrender its contractor license for review

Public Contract Code section 5105 says a bidder who claims a mistake is “prohibited from participating in further bidding on the project” on which the mistake was claimed. The 10 percent penalty belongs to section 4110 (subcontractor listing violations), and section 5105 sets no statewide suspension or license surrender.

Start free

CAContractorLicenseExam · Topics · Exam guide · Sample questions